Define the operation and responsibility
Specify which activities are included: cutting, stitching, finishing, checking or packing. Record who supplies fabric/trims, approves samples, provides transport and pays for rework. A complete-garment rate and a single-operation rate need different work content. Compare rates only after matching scope.
Calculate a realistic output scenario
Illustrative balanced-line capacity: 10 operators × 480 available minutes × 65% effective efficiency ÷ 12 standard minutes per garment = 260 garments per day. This assumes a comparable line-balanced standard, suitable skill and equipment, and no additional constraint. If the standard time already incorporates a particular allowance, understand it before applying another factor. Use observed output to replace assumptions.
Find the controlling constraint
- Compare capacity at cutting, key sewing operations, decoration and finishing.
- Check operator skills, machine availability, changeovers and material readiness.
- Record inspected/accepted output separately from pieces passing one operation.
- Allow for the actual mix of sizes, styles and rework rather than applying one universal efficiency.
Allocate daily cost to good output
If the included daily operating cost were ₹10,400 and accepted daily output 260 pieces, allocated cost would be ₹40 per piece. At only 200 accepted pieces, it would be ₹52. That example shows why a rate based on theoretical maximum output can understate cost. Add any separately agreed order charges and commercial allowance; these figures are not recommended job-work rates.
Use the agreement to close handovers
Keep a record of material received, operation/sample revision, expected output, inspected acceptance, defects and dispatch quantities. Agree how waiting time, changes and rework are recorded. Review actual cost/output after the first run rather than promising the same rate for every style.
Examples illustrate a method; they are not market quotations, supplier certifications or guarantees of commercial results. Confirm your own assumptions and the requirements of the specific order.